Hold the sheet in place with a short 2x4 spacing block snap tie and c bracket placed toward the top of the panel and nail the bottom of the sheet to the joint cover wale.
													
																	How to form a concrete wall with snap ties. 
								
	
		
	
																	Set additional panels by nailing them to the joint cover wale and securing them to the previous panel with a small wood cleat. 
																	Insert pipe over tie then use the end of pipe as a lever and. 
																	Get a piece of steel pipe the proper diameter to fit over the foundation tie. 
																	After the plywood is stripped the plastic cone and exposed tie end are removed with a twist. 
															
													
								
	
		
	
																	Odd end oe snap ties measure 4 3 4 at one end and 8 1 4 at the other end plus the wall thickness. 
																	The plastic cones set the wall dimension and cover the plywood hole. 
																	Ocm inc stsec 6hh 6 wall x 4 3 4 end hex head plastic cone snap ties can be used with either the 1 or 2 forming systems with 3 4 plywood. 
																	This snap tie forming method is used for retaining and standard walls batter walls bridges concrete signs footings etc. 
															
													
								
	
		
	
																	Every snap tie includes two 1 plastic cones. 
																	Concrete snap tie installation. 
																	Purchase enough concrete to fill the hole then add it all to a big mixer with a pouring ramp. 
																	They are held in place by a snaptie wedge or jahn bracket. 
															
													
								
	
		
	
																	Use a screed to smooth out the concrete immediately before it has a chance to set. 
																	Have the pipe cut to approximately 2 feet in length. 
																	Mix and pour concrete to fill the footer hole. 
																	Hook the tape measure to the bottom edge of the form measure up 1 foot.